Progress in construction

Progress in construction RC “SHCHASLYVYI PLATINUM” Lviv, September 2020

• installation and warming of the ventilated facade proceeds;

• the installation of the lighting system continues;

• plastering of surfaces is completed on the 22nd floor inclusive, floor screed - from 4 to 17 floors;

• work on the distribution of water supply, sewerage and heating systems is completed;

• fire hydrant mains are ready and removed from the pumping station to the technical floor;

• finishing works and plastering have been completed in the roof boiler house;

• interior decoration works (4-6 floors) are underway