• installation and warming of the ventilated facade proceeds;
• the installation of the lighting system continues;
• plastering of surfaces is completed on the 22nd floor inclusive, floor screed - from 4 to 17 floors;
• work on the distribution of water supply, sewerage and heating systems is completed;
• fire hydrant mains are ready and removed from the pumping station to the technical floor;
• finishing works and plastering have been completed in the roof boiler house;
• interior decoration works (4-6 floors) are underway