• the monolithic structures installation of residential and commercial parts of the complex and underground parking has been completed;
• completion of the ceramic block external walls and the gas block internal walls masonry;
• electrical work on 3-15 floors completion;
• plastering works on 5-12 floors completion;
• 80% of fire works completion;
• plumbing work start;
• installation of railings for air conditioners, completed by 20%;
• windows installation completion